Resource Leveling: Complexity of a UET two-processor scheduling variant and related problems
Abstract
This paper mainly focuses on a resource leveling variant of a two-processor scheduling problem. The latter problem is to schedule a set of dependent UET jobs on two identical processors with minimum makespan. It is known to be polynomial-time solvable. In the variant we consider, the resource constraint on processors is relaxed and the objective is no longer to minimize makespan. Instead, a deadline is imposed on the makespan and the objective is to minimize the total resource use exceeding a threshold resource level of two. This resource leveling criterion is known as the total overload cost. Sophisticated matching arguments allow us to provide a polynomial algorithm computing the optimal solution as a function of the makespan deadline. It extends a solving method from the literature for the two-processor scheduling problem. Moreover, the complexity of related resource leveling problems sharing the same objective is studied. These results lead to polynomial or pseudo-polynomial algorithms or NP-hardness proofs, allowing for an interesting comparison with classical machine scheduling problems.
Turn this paper into a full lesson
ArcXiv compiles a staged curriculum from this paper: 8-12 lessons across beginner → advanced, synthesised section guides, visuals, flashcards, a quiz, exercises, and on-demand deep dives per section. Grounded in the abstract, never invented.