Impact of Data Center Load on Co-Optimized Generation and Transmission Expansion Planning with Embedded Unit Commitment
Abstract
The rapid growth of hyperscale data centers challenges grid expansion planning, yet existing studies focus largely on operational flexibility rather than long-term investment decisions. This paper examines how large data center loads sited at multiple buses affect co-optimized Transmission Expansion Planning (TEP) and Generation Expansion Planning (GEP). The problem is formulated as a multi-year, Unit Commitment (UC)-embedded mixed-integer linear program on the modified IEEE 24-bus Reliability Test System (RTS-24) with Electric Reliability Council of Texas (ERCOT)-calibrated renewable energy profiles. A 500 MW data center load, about 17.5% of the base-year peak, is allocated across four buses by voltage level, generation headroom, renewable co-location, and network connectivity. Integrating this load raises the 15-year net present value of total system cost by 1,794 million USD (+61.6%) and the system-average locational marginal price (LMP) by 45.2%, with operating cost dominating capital investment (84.2% versus 15.8%). Renewable curtailment remains negligible: existing renewables are already near full utilization, so the added demand is served almost entirely by incremental thermal generation. Most notably, the load shifts the optimal plan from transmission-only to generation-only, replacing the base-case 230 kV reinforcement with a new 400 MW combined-cycle gas turbine and showing that strategically sited generation can substitute for network reinforcement.
Create a lesson
Metadata
- Categories
- eess.SY, cs.SY
- Comments
- 6 pages, 2 figures, 3 tables. Accepted to the 2027 IEEE Texas Power and Energy Conference (TPEC)
Related papers
Virtual Transmission Lines from Data Center Workload Migration: Coordinated Multi-Year Transmission Expansion Planning
Shared title terminologyeess.SYMengxin Zhu, Qian Kai, Yadong Liu et al.
Quantifying the hosting capacity value of workload flexibility for AI data centers: A two-stage electricity-computation co-optimization framework
Shared title terminologyeess.SYJiakai Wu, Wei Sun, Pengyu Ren et al.
Degradation Aware V2G Dispatch for Co-Optimization of Parking Facility and Edge Data Center Located in the Airport Campus
Shared title terminologyeess.SYAbdullah Al Mehadi, Hamed Haggi, Chinmay Morankar
Learning Stability of Replay-Based Co-Optimization for Transmission Expansion under Strategic Bidding
Shared title terminologyeess.SYTomonari Kanazawa, Hikaru Hoshino, Eiko Furutani
Data Center-Aware Load Pickup in Power System Restoration
Shared title terminologyeess.SYYousef Abudyak, Saleh Sadeghi Gougheri, Mohsen Alizadeh et al.
Which Data-Center Load Models Can Be Trusted? An Evidence-Graded Review of Dynamic Modeling and Validation for Large Computational Loads
Shared title terminologyeess.SYDileep Cheerla